Update – end of the 2nd week
The builders have completed about 25% of the work, and the build is on target:
- Excavation work is complete
- Strip foundations are complete
- The sub-structure is built up to adjoining floor level
- The drain tie-in is installed
- Lighting for the back corridor is complete
- Completed the floor for the new back lobby between the Legion and our room
Next phase of work is to back-fill the foundations and start building the Phase 2 interior / corridor walls