Another Few Bricks in the Wall

Update – end of the 2nd week

The builders have completed about 25% of the work, and the build is on target:

  • Excavation work is complete
  • Strip foundations are complete
  • The sub-structure is built up to adjoining floor level
  • The drain tie-in is installed
  • Lighting for the back corridor is complete
  • Completed the floor for the new back lobby between the Legion and our room

Next phase of work is to back-fill the foundations and start building the Phase 2 interior / corridor walls