Progress at 14th Jan 2020 / Meeting 16th Jan reminder

A new year has arrived, the Builders are back at work after the seasonal break and the end is very nearly in sight.

  • Right hand side, door to Legion / Loos at back right corner

Progress since last report is:

  • The Electrician has completed the main wing runs and installed the fire alarm cable
  • The Joiner has installed most of the plaster board
  • The 3 door frames are ready for the new doors
  • The Joiner has re-positioned the Fire Exit doors from the Legion in the rear corridor
  • The step and platform within the room to the back exit door (to the back corridor) are complete

Total progress to the project plan is about 82%

Can we also remind folk that the bi-monthly meeting is THIS THURSDAY, 16th Jan at 10:00 a.m. (not the usual afternoon meeting), upstairs in the Legion.  Many thanks