A new year has arrived, the Builders are back at work after the seasonal break and the end is very nearly in sight.
Progress since last report is:
- The Electrician has completed the main wing runs and installed the fire alarm cable
- The Joiner has installed most of the plaster board
- The 3 door frames are ready for the new doors
- The Joiner has re-positioned the Fire Exit doors from the Legion in the rear corridor
- The step and platform within the room to the back exit door (to the back corridor) are complete
Total progress to the project plan is about 82%
Can we also remind folk that the bi-monthly meeting is THIS THURSDAY, 16th Jan at 10:00 a.m. (not the usual afternoon meeting), upstairs in the Legion. Many thanks