Hiding an awful lot of previous work, the concrete floor is now down…
![](http://banchorymensshed.org/wp-content/uploads/2019/12/Concrete-down.jpg)
Hmm, seems like a nice pair of goalposts…
Overall progress is approximately 60%. This week has seen:
- Completion of backfilling of the foundations
- Installation of the underfloor insulation and concrete floor
- Complete the foundations for the front fittings
Next week the builder will render the passage wall to match the Legion and commence timber framing of the inside and installing insulation.