31st Jan 2020 – Tunnel, Lights, Action

Very little left to do now, basically the fire alarm hookup (Thursday) and painting.

In this last couple of weeks we’ve seen the Ames Taping, Electrician Second Fix and Plumber Second Fix all complete.

  • Only final finishing required

Progress at 14th Jan 2020 / Meeting 16th Jan reminder

A new year has arrived, the Builders are back at work after the seasonal break and the end is very nearly in sight.

  • Right hand side, door to Legion / Loos at back right corner

Progress since last report is:

  • The Electrician has completed the main wing runs and installed the fire alarm cable
  • The Joiner has installed most of the plaster board
  • The 3 door frames are ready for the new doors
  • The Joiner has re-positioned the Fire Exit doors from the Legion in the rear corridor
  • The step and platform within the room to the back exit door (to the back corridor) are complete

Total progress to the project plan is about 82%

Can we also remind folk that the bi-monthly meeting is THIS THURSDAY, 16th Jan at 10:00 a.m. (not the usual afternoon meeting), upstairs in the Legion.  Many thanks