The Phase 2 build continues on track. Quite a visible difference this week due to the wall. The work completed was as follows:
- The walls were completed to ceiling level
- The foundations were back-filled ready for under-floor insulation and floor
- The drain is in for the sink
- The door opening between the social area and the “Phase 1” Workshop is broken through and initially boarded up
Next week we expect to see the foundations completed for the front fittings, the underfloor insulation installed and the floor concreted, plus the start of the timber framing